Weather Delays Final Paving of Fourth Street

Date: 
08/09/12

 

Today's rain has pushed back the final paving of Fourth Street from Ohio Street to Garfield Street. The current plans (weather permitting) are as follows:

 

  • Milling the temporary street transitions - Friday 8/10
  • Intermediate asphalt Main Street to Garfield Street - Friday 8/10 and Saturday 8/11 (if needed)
  • Surfacing Ohio Street to Lincoln Street - Tuesday 8/14
  • Surfacing Lincoln Drive to Garfield Street - Wednesday 8/15
  • Stripping and other street painting - Wednesday 8/15

 

There will be no street parking available in the identified areas on 8/14 and 8/15 while the street is resurfaced. Intersections and alleys in this area will also be closing on an as needed basis. Please use alternate routes to access businesses in the construction area during the first part of next week.