09/05/12

 
The Village recently contracted with Newcomer Concrete Services to replace to the curb and gutter on Seventh Street from Main Street to Hanover Street. The scope of the project includes replacing the entire curb and gutter on the north side of the street and some of the curb and gutter on the south side, as well as milling and resurfacing the street with new asphalt.
 
A pre-construction meeting was recently held and the following work schedule has been outlined for the project:

  • Monday, September 17 – Remove curb on south side of street
  • Tuesday, September 18 - String and pour curb on south side of street
  • Wednesday, September 19– Backfill around curb on south side of the street
  • Monday, September 24 - Remove curb on north side of street
  • Tuesday, September 25 – String and pour curb on north side of street
  • Wednesday, September 26 – Backfill around curb on north side of the street
  • Thursday, September 27 – Mill asphalt off of street
  • Friday, September 28 – Resurface street

Traffic in this area will be maintained during the construction work. Please use extra caution if you must be in this area.

Town Crier Blog

Posted 10/13/17 by the Town Crier
Posted 10/06/17 by the Town Crier
Posted 09/25/17 by the Town Crier
Posted 09/22/17 by the Town Crier